The Paramaribo District Court ruled on August 28th in two consolidated summary proceedings concerning Nickeriestraat, where a call center is planned for the corner of Marowijnestraat. This was reported by Dagblad Suriname.
A group of 47 local residents, who sued the Surinamese State, entrepreneur Hemradj Dassasingh, Stichting Real Estate International Group, and Roman Jayantsingh, were declared inadmissible or had their claims dismissed, according to the ruling. They were also ordered to pay legal costs: SRD 7.500 for NV cs and SRD 7.500 for the State. The case was consolidated with a second case brought by the residents against the same parties, including the Ministry of Public Works and the district commissioner. full judgment (pdf) can be read here.
UPDATE September 5, 2025 – On the Surinamese channel Apintie gave Dassasingh, the accused entrepreneur involved as a project developer, says he has been primarily affected by the construction delays and the theft of building materials. He states that all permits are in place for construction and that the call center will create additional jobs.
Protest from local residents
From the moment the plans for the call center were announced, local residents have fiercely protested. They fear that the arrival of a large office in their neighborhood will seriously affect the quality of life. The neighborhood is considered a quiet area, with schools, sports fields, and family homes nearby. Residents have voiced their grievances through protest signs, petitions, media appearances, and ultimately, legal action. They believe a 24-hour commercial operation is inappropriate in this residential area and undermines the neighborhood's social function. They fear traffic, parking, and noise pollution. Residents argue that there has been no neighborhood survey or consultation process and feel sidelined.
Interim injunction
Local residents have in April 2025, an emergency summary proceeding was filedto immediately halt construction. The court scheduled a first hearing for April 24, 2025. During the proceedings, two summary proceedings—one aimed at revocation of the permit and one aimed at a construction freeze—were consolidated into a single case. Construction has been temporarily halted pending the ruling. It is not yet known whether the neighborhood will take further legal action, such as legal proceedings or an appeal.
(text continues after the image)
Ziptone previously reported that several large facility contact centers (such as Concentrix, ETB, Yource, and Teleperformance) indicated they were not interested in the new location. Only WEngage kept the possibility open but had no definitive plans to occupy the building. The building may be constructed on a speculative basis: the developer is building the center in the expectation of finding a tenant or operator, with the overall purpose (contact center) already established.
(Ziptone/Dagblad Suriname/Apintie)
This article may be updated